  3. title: "What a risk is"
  4. icon: "🛡️"
  5. description: "Where the border lies between a risk, a bug and a task; how to rate probability and severity; which risk is serious; what to write so that a risk can be held."
  6. ---
  7. A **risk** is an event that has not happened yet but may, and then will harm the product, the customer, the contractor or third parties. One record is one event.
  8. ## The border
  9. | What | It is | Where it goes |
  10. |---|---|---|
  11. | May happen, has not happened yet | a risk | [Risks](/quality/risks.md) |
  12. | Already happened, there is a symptom | a bug or an incident | [Bugs](/work/bugs.md); the risk moves to "Occurred" |
  13. | Must be done to reduce the risk | a task | [Tasks](/work/tasks.md); the risk refers to the measure in words in `mitigation` |
  14. | We decided to live with the risk | a decision | [Decisions](/knowledge/decisions.md); the risk goes to "Accepted" with the `decision` field |
  15. ## Rating
  16. Probability and severity are on a scale from 1 to 5; the labels of the scale are in the collection's schema.
  17. - **Severity** is rated by the worst plausible outcome, not the average.
  18. - **Probability** is how often it will happen over the life of the project if there are no measures at all.
  19. A **serious risk** is severity 4 or 5, or probability × severity of at least 12. While a serious risk is open or being mitigated, it is covered by a test or an accepted decision (a norm of the `testing` package, if it is installed).
  20. ## What to write so that a risk can be held
  21. - **Who is responsible** (`owner`): the person who moves the risk along the contour.
  22. - **How we will notice** (`signal`): what we will see when the risk starts to come true: an alert, a line in the journal, a drop in an indicator.
  23. - **How we reduce it** (`mitigation`): measures in the product or the process. "Keep an eye on it" is not a measure.
  24. - **Why it is accepted** (`acceptedBecause`) or a **decision** (`decision`): when we consciously do not reduce the risk.
  25. Example: "The agent publishes an unverified fact in a letter to a client"; severity 4, probability 3; we notice by a complaint or by a spot check of letters; we reduce it with a source link for every fact and a human's confirmation before sending.