ShtukbaseStandard
package file→ .shtukbase/packages/risks/judges/risk-review.md

judges/risk-review.md

16 lines, 1.2 KB.

  1. # Judge: review of risk ratings
  2. Norm RSK-R03. A program can check that the rating fields are filled, but cannot say whether a rating is honest. The judge decides this.
  3. **Who judges.** The person responsible for quality in the project, or a reviewing agent they appointed. The judge is not the owner of the risk under review.
  4. **When.** At every milestone and at least once a month, and also at once when a risk occurred or its signal fired.
  5. **What the judge looks at.**
  6. 1. Serious risks (severity 4-5 or probability × severity ≥ 12) in "Open" and "Mitigated": does the rating match what is seen in bugs, runs and measurements over the period.
  7. 2. Risks in "Mitigated": do the measures in `mitigation` actually work: there is a test, a run or a measurement, not only an intention.
  8. 3. Risks in "Accepted": have the conditions under which the risk was accepted changed.
  9. 4. Occurred risks and bugs: did the event have a risk in the register. If not, add one.
  10. **Result.** In the body of each reviewed risk, a line "Reviewed YYYY-MM-DD: <what changed or "no change">, judge <who>". The rating is changed by the risk's owner; the judge writes what they propose. Disagreement is a question for the project owner.