- # Judge: review of risk ratings
- Norm RSK-R03. A program can check that the rating fields are filled, but cannot say whether a rating is honest. The judge decides this.
- **Who judges.** The person responsible for quality in the project, or a reviewing agent they appointed. The judge is not the owner of the risk under review.
- **When.** At every milestone and at least once a month, and also at once when a risk occurred or its signal fired.
- **What the judge looks at.**
- 1. Serious risks (severity 4-5 or probability × severity ≥ 12) in "Open" and "Mitigated": does the rating match what is seen in bugs, runs and measurements over the period.
- 2. Risks in "Mitigated": do the measures in `mitigation` actually work: there is a test, a run or a measurement, not only an intention.
- 3. Risks in "Accepted": have the conditions under which the risk was accepted changed.
- 4. Occurred risks and bugs: did the event have a risk in the register. If not, add one.
- **Result.** In the body of each reviewed risk, a line "Reviewed YYYY-MM-DD: <what changed or "no change">, judge <who>". The rating is changed by the risk's owner; the judge writes what they propose. Disagreement is a question for the project owner.